2015 Municipal Water Project

Follow this blog for construction updates on the municipal water project.

View All Posts

Aug 22

Permit Deadline this Friday

Posted on August 22, 2016 at 4:17 PM by Andy Pederson

As part of the water project 3 permits were required for every home.f permits were not pulled prior to the work they are subject to a double fee. Double fees will be assessed for permits not pulled before August 26.  More details on the permits are below:

CHECK THE STATUS OF YOUR HOME HERE

1.       A lateral permit (for the line running from your house to the street). This should have been pulled by your plumber or contractor who did your lateral. Please contact them to verify if your home does not have a permit number listed on our spreadsheet.

 

2.       Interior plumbing permit. This was for the connection inside your home and the separation of the well from the house. This should have been pulled by your plumber. Please contact them to verify if your home does not have a permit number listed on our spreadsheet.

 

3.       Well operation OR well abandonment permit.  A decision must be made on your well. If you keep the well for outside watering, a well operation permit is required. If you are no longer using your well, a well abandonment permit is required.


For any questions, please call Village Hall at 414-351-8811 x 1